When a major project is announced during an election year, you can pretty much bet some aspect of the work will go sideways.

That's what happened to the Plessis Road widening and underpass project, a major Winnipeg roadwork, rail-underpass and pipeline realignment that leapfrogged into existence in the midst of a dual federal and provincial election cycle in 2011.

The project had an initial $77-million budget and a 2014 completion date. This initially seemed unlikely, due to the complexity of negotiating with both pipeline and railway companies. But the city, province and Ottawa forged ahead, thanks to commitments made to voters in 2011.

Last week, city council was told the project is behind schedule and over budget to the tune of $7 million -- and Ottawa may not pick up its $25 million of the now-$84-million price tag because the improbable original deadline has not been met.